Heavy Roof Truss
 
 
Bahrain Coke Calcining Plant


 
 
 
 
General Contractor
Kooheji Contractors W.L.L

Client
Aluminium Bahrain

Scope of Work

TTJ erected the steelwork for this project including design of temporary work. The Bahrain Coke Calcining Plant comprised of 17 main trusses, each about 92 m long and 40 tons. Each truss was broken into 8 segments to facilitate installation by crane.

The challenge in this project was its arch shape and long span truss. In fact, this is the longest span truss in
Bahrain to-date.